https://energy.prayaspune.org/our-work/policy-regulatory-engagements/rp75of2025   MSEDCL seeks additional costs : (a) Rs. 55,600 crores in Capex, (b) Rs. 69,800 crores due to errors in MERC power procurement model (c) Rs. 3,272 crores due to errors in agricultural demand estimation methodology (d) Rs. 11,751 crores due  to dispensations approved by   Supreme Court, APTEL and MERC in various  orders. MSEDCL has also claimed erroneous classification of hotel industry and specification of time-of-day tariffs with clarifications on banking restrictions.  

https://api.sci.gov.in/supremecourt/2015/14553/14553_2015_6_1501_62958_Judgement_06-Aug-2025.pdf  

https://cercind.gov.in/2025/orders/38.pdf

https://aptel.gov.in/sites/default/files/2025-04/RP%201%20of%202025%20.pdf

 